60 man can do a work in 40 days. How long will it take 40 men to complete the same work?
- 60 days
- 30 days
- 29 days
- 23 days
Explanation
- Men × Days = Total Work
- Formula
- M1 X D1 = M2 X D2
- 60 × 40 = 40 × D
- D = (60 × 40) ÷ 40
- D = 60 days