If 5 workers can complete a task in 12 days, how many worker-days are required to complete the task?
- 50 worker-days
- 60 worker-days
- 65 worker-days
- None of these
Explanation
Worker-days = Workers × Days
= 5 × 12 = 60 worker-days.