If 15 workers can complete a job in 20 days, how many workers are required to complete the same work in 10 days, assuming all workers have equal efficiency?
- 30
- 32
- 34
- None of these
Explanation
Given:
15 workers complete the work in 20 days
Step 1: Find total work
Total work = Number of workers x Number of days
Total work = 15 x 20 = 300
Step 2: Find workers needed for 10 days
Let the required number of workers = W
W x 10 = 300
W = 300 / 10
W = 30
Last verified on 13-11-2026