If it takes 6 people 6 days to do a job. How many days would it take 2 people working at the same rate to do the job?
- 6
- 12
- 16
- 18
Explanation
If it takes 6 people 6 days to do a job, the total amount of work can be considered as 6 people × 6 days = 36 person-days.
For 2 people to do the same amount of work:
Number of days = 36 person-days / 2 people = 18
So, it would take 2 people 18 days to do the job.