If 500 people complete a work in 25 days and they work for 12 days, then 300 people will complete the remaining work in how many days?
  1. 15 days
  2. 21⅔ days
  3. 25 days
  4. None of these
Explanation

Total work = people × days = 500 × 25 = 12500 person-days

Work done in first 12 days by 500 people = 500 × 12 = 6000 person-days

Remaining work = 12500 - 6000 = 6500 person-days

Now 300 people will do the remaining work.  

Days needed = Remaining work / people = 6500 / 300 = 21⅔ days


Last verified on 05-09-2026

Related MCQs

  1. 17.5 years
  2. 18.5 years
  3. 19.5 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 15 days
  2. 21⅔ days
  3. 25 days
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 10 years
  2. 14 years
  3. 12 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 20 years
  2. 24 years
  3. 25 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 6 years
  2. 8 years
  3. 10 years
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com