A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work was finished one day earlier. How many days would it have been delayed if 5 more men were not employed?
- 4 day
- 2 day
- 1 day
- None
Explanation
men completed the remaining job in .
Now the same job has to be done by .
We know that,
Required time
Delayed time
Related MCQs
- Father
- Uncle
- Grandfather
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 15
- 20
- 25
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 8
- 7
- 6
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 6 days
- 5 days
- 7 days
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 10
- 15
- 5
- None of these