12 men work 8 hours a day to complete a piece of work in 10 days. to complete the same work in 8 days, working 15 hours a day, the number of men required is.
  1. 6
  2. 8
  3. 10
  4. 12
Explanation

w = Men x Days x Hours 

12 x 8 x 10 = 960

 960 / 8 x 15 = 8 Men