A and B can do a piece of work in 12 days, B can C in 8 days and C and A in 6 days. How long would B take to do the same work alone?
- 24
- 32
- 30
- 48
Explanation
Given:
Time taken by A and B to complete the work = 12 days
Time taken by B and C to complete the work = 8 days
Time taken by C and A to complete the work = 6
Formulae used:
Time = Total work / Efficiency
Calculation:
Let us assume the total work is 1 unit.
⇒ A and B complete 1 unit work in 12 days → (A and B)'s 1 day's work = 1/12
⇒ B and C complete 1 unit work in 8 days → (B and C)'s 1 day's work = 1/8
⇒ A and C complete 1 unit work in 6 days → (A and C)'s 1 day's work = 1/6
Adding everyone's 1 day's work:
= A, B, and C's 1 day's work = 9/48
⇒ B's 1 day's work =
⇒ B's 1 day's work =(9/48)
⇒ B completes 1/48 of the work in 1 day.
Therefore, B alone will take 48 days to complete the work.
Related MCQs
- 80 km/h
- 72 km/h
- 100 km/h
- None of these
اس سوال کو وضاحت کے ساتھ پڑھیں
- 150°
- 155°
- 160°
- 165°
اس سوال کو وضاحت کے ساتھ پڑھیں
- 5 km
- 10 km
- 15 km
- 20 km
اس سوال کو وضاحت کے ساتھ پڑھیں
- 20 minutes
- 30 minutes
- 45 minutes
- 60 minutes
اس سوال کو وضاحت کے ساتھ پڑھیں
- 22 sec
- 20 sec
- 24 sec
- None of these