A can complete a work alone in 10 days. A & B together complete it in 8 days. How many days can B alone complete the same work?
  1. 30 days
  2. 40 days
  3. 20 days
  4. 25 days
Explanation
Step 1: A’s 1-day work


Step 2: A + B’s 1-day work

Step 3: B’s 1-day work

Find LCM of 8 and 10 = 40:

Step 4: Days B alone will take