If 15 workers can complete a job in 20 days, how many workers are required to complete the same work in 10 days, assuming all workers have equal efficiency?
  1. 30
  2. 32
  3. 34
  4. None of these
Explanation

Given:  

15 workers complete the work in 20 days  

Step 1: Find total work  

Total work = Number of workers x Number of days  

Total work = 15 x 20 = 300  

Step 2: Find workers needed for 10 days  

Let the required number of workers = W  

W x 10 = 300  

W = 300 / 10  

W = 30  


Verified & Updated

Related MCQs

  1. Father
  2. Uncle
  3. Grandfather
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 15
  2. 20
  3. 25
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 8
  2. 7
  3. 6
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 6 days
  2. 5 days
  3. 7 days
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 10
  2. 15
  3. 5
  4. None of these
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com