After setting up a surveying instrument, the first reading taken is called:
سروے کے آلے کو نصب کرنے کے بعد لی جانے والی پہلی ریڈنگ کو کیا کہا جاتا ہے؟
  1. Fore sight
  2. Intermediate sight
  3. Back sight
  4. Reduced level
Explanation
  • Back sight: The first reading taken after setup, always on a point of known elevation.

Additional information 

  • Fore sight: The last reading taken before moving the instrument.
  • Intermediate sight: Any reading taken between the back sight and fore sight.
  • Reduced level: A calculated ground height, not an instrument reading.

Related MCQs

  1. Reduced Level (R.L.)
  2. Height of Collimation
  3. Height of Instrument (H.I.)
  4. Fore Sight (F.S.)
اس سوال کو وضاحت کے ساتھ پڑھیں

سروے کے آلے کو نصب کرنے کے بعد لی جانے والی پہلی ریڈنگ کو کیا کہا جاتا ہے؟
  1. Fore sight
  2. Intermediate sight
  3. Back sight
  4. Reduced level
اس سوال کو وضاحت کے ساتھ پڑھیں

شاہراہوں کی سیدھ (الائنمنٹ) عموماً کس راستے کے ساتھ مقرر کی جاتی ہے؟
  1. Valley line
  2. Contour line
  3. Ridge line
  4. Drainage line
اس سوال کو وضاحت کے ساتھ پڑھیں

سروے کی زنجیر کے دستوں (ہینڈلز) کے لیے کون سا مواد استعمال کیا جاتا ہے؟
  1. Steel
  2. Iron
  3. Brass
  4. Aluminum
اس سوال کو وضاحت کے ساتھ پڑھیں

  1. 50
  2. 100
  3. 150
  4. 200
اس سوال کو وضاحت کے ساتھ پڑھیں

All Rights Reserved © TestPointpk.com