If 5 workers can finish a task in 4 days, how many days will it take 10 workers to finish the same task?
- 2 days
- 4 days
- 6 days
- 8 days
Explanation
Given:
- 5 workers → 4 days
- 10 workers →? days
Using the formula:
Workers × Days = Constant
5 x 4 = 10 x X
20 = 10x
x=20/10
x = 2 days