If 72 workers can do a piece of work in 40 days, in how many days will 64 workers complete the same work?
- 50
- 45
- 40
- None of these
Explanation
Total work = 72 workers 40 days = 2880 worker-days
For 64 workers:
Days = 2880 / 64 = 45 days